Thread: [Solved] Start & Finish Date/Time
View Single Post
 
Old 04-05-2016, 06:13 AM
JulieS JulieS is offline Windows 7 64bit Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

What is the duration of the Project Summary task - line 0. Without any tasks the duration should be zero and start date/time = finish date/time