Start & Finish Date/Time
View Single Post
03-24-2016, 06:22 AM
JulieS
Windows 7 64bit
Office 2013
Expert
Join Date: Dec 2011
Location: New England
Posts: 1,693
My guess is the Project start time was not updated when the calendar was changed to start at 8:30. What is the start time in the calendar? (Change working time). What is the default start time (File > Options, Schedule).