My suggestion is to create a task calendar where the only working time is the Board meetings scheduled monthly. Assign that task calendar to the "Present to board" task. It will be scheduled only for the schedule you've set in the task calendar.

Do post back if you need further directions on either creating the task calendar or making the assignment of the task calendar to the task.