With the exception of task 6 - your tasks are manually scheduled without duration, start or finish. You have a task calendar assigned to each task - versus setting up the project calendar to the correct schedule. Because your tasks have not schedule the 'worker' resource is not overallocated.
Change your tasks to autoschedule - remove the task calendar. Set the priority and level using priority, standard.
|