Thread: [Solved] Work semi completed
View Single Post
 
Old 02-17-2016, 08:05 AM
JulieS JulieS is offline Windows 7 64bit Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

You are mixing and matching % complete which is a duration measurement and % work complete. In order to measure % work complete - 17% - you need to assign a resource. In order to track work on specific days - you'll need a timescaled view such as the Task Usage view.