View Single Post
 
Old 02-16-2016, 07:20 AM
JulieS JulieS is offline Windows 7 64bit Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

I have stepped through creating the Baseline work report. As I stated earlier - I see full data. I've attached the Excel spreadsheet.

The report pulls Baseline Work, Baseline1 Work, Baseline 2 work.

I didn't step through the entire process of creating the S-curves - just grabbing the data out of Project. That part works fine.
Attached Files
File Type: xlsx Schedule report.xlsx (26.0 KB, 14 views)
Reply With Quote