Thread: [Solved] Work semi completed
View Single Post
 
Old 02-01-2016, 03:26 AM
c991257 c991257 is offline Windows 7 64bit Office 2013
Advanced Beginner
 
Join Date: Mar 2014
Location: Zambia
Posts: 61
c991257 is on a distinguished road
Default Work semi completed

Hi,

I am trying to puzzle out how how to show when certain work was carried out.

Let's say I have a task that takes 20 days.
5% was carried out on 01 Jan
10% was carried out on 04-5 Jan
85% remains and will be done at a later stage.

How do I show when the work, i.e. the actual days, was actually carried out?

BTW: I'm not using resources in the programme - only tasks.

/Møller
Reply With Quote