Work semi completed
Hi,
I am trying to puzzle out how how to show when certain work was carried out.
Let's say I have a task that takes 20 days.
5% was carried out on 01 Jan
10% was carried out on 04-5 Jan
85% remains and will be done at a later stage.
How do I show when the work, i.e. the actual days, was actually carried out?
BTW: I'm not using resources in the programme - only tasks.
/Møller
|