I'm not sure I follow completely. Are task 4 (for example) the exact same task - same dates, same resources? You can create dependencies (Finish to start, Start to Start, etc.) between tasks in different schedules - but you cannot have the same exact task appear in multiple projects.
Can you tell us a bit more about your scenario - we'll try to be more helpful.
|