Hi Paul,
I'm sorry there is no method to have the cost calculated based upon 7.5 hours per day but have the duration based upon 6.5 hours per day. Cost is always based upon work - so changing assignment units will change the duration - but the work will remain the same. The best I can suggest is to adjust the cost so the rate of 7.5 per day is applied to a 6.5 hour day.
|