Hi,

I assume that you want the Gantt chart to have Month 1, Month 2, etc. rather than the dates.

Right click on the timeline (where it gives the date and days of the week on a new plan) and select timescale.

The default is to have 2 levels and on a new plan this will be weeks and days. From the Units list on both Middle Tier and Bottom Tier, scroll to relevant unit and select it, and on the Label do the same.

Hope this is what you meant.

Regards,
Margaret