Default Duration didn't copy to Baseline Duration when I saved a Baseline

I created a schedule and entered task names, durations, and logic (predecessors/relationships) and saved the schedule. At a later date, I set a baseline. When I started adding columns to the Tracking Gannt view, it appeared that no Baseline information was copied over.

If I understand the previous answer, the Baseline Duration column should have been populated with the information that I had already entered in the Duration column, correct? Is there a way to make Project copy this information over?