Seperate Cost per Resource Group and Taskname
Hello everybody,
I´m currently planing a bigger project.
I already have defined various tasks with subtasks and already assigned resources and materials to every subtask.
My problem is the following:
My resources are divided into different Resource Groups (in reality these are different Companys which I´m going to contract and pay).
For the payment I would like to know per task the sum of the cost for each resource group/company e.g. two resources of the same company are working on one task so I would like to see automatically how much money I have to pay to the company per task.
Currently I just managed to see the total cost per task or the cost per resource in each task.
Would be great if anybody could help me.
Best regards