Default Variable Task Length aka "Time Zones"

Hello all,

I'm a production engineer in the oil and gas business. Part of my position is well planning and to a degree scheduling. Our business unit is now starting to utilize MS Project so we're all a bit new.

for us, drilling a well offshore in the winter will take 15% longer than in the summer. As we stack up multiple wells and move further into the future, is there a way to set this up in project so that when the well schedule changes and pushes wells into the +15% "time zone" the task length will automatically increase?