In a text field:
switch([% Complete]=100,"blue",ProjDateDiff([Current Date],[Finish])/[Minutes Per Day]<=5,"red",ProjDateDiff([Current Date],[Finish])/[Minutes Per Day]<=10,"amber",ProjDateDiff([Current Date],[Finish])/[Minutes Per Day]>10,"green")