Start date of successor
I am having an issue PM 2013 where my successor date starts on the same day as the predecessor ends. This causes resourcing issues.
For e.g.
Task one ends on the 15th with duration 1 day
Task two starts on the 15th.
Why is this happening and how can I get it to start on the next day is my first question.
My second questions is if the resource is allocated to spend 5 hours on the first task, technically he has 3 hours left on that day (assuming an 8 hour day) and the task is set to 1 day duration. So does PM know that and allocates 3 hours to task on the 15th and thats why it sets the start date of task 2 to the same day?
Thanks
|