No it will not change because the successor task has an Actual Start date and Actual Start dates trump scheduled start dates. If a successor has been started, why would you want to change the start date later on?
However, if you have allowed splits in in-progress tasks (Options, Schedule) the successor task's remaining work should be scheduled based upon the original link relationship.
|