Hopefully a Easy Resourcing Questions
View Single Post
08-21-2015, 01:15 PM
JulieS
Windows 7 64bit
Office 2013
Expert
Join Date: Dec 2011
Location: New England
Posts: 1,693
Sure - go into the Task Usage view and modify the scheduled work for the week. It will recalculate the assignment units for that one week.