Default Cost resource not taken in real cost

Hello,

In my planning I have defined one resource called HW which I have defined as as cost resource.
I want to use this to log cost for some HW equipments.
So on some task I assigned this HW resource and give it the value of my equipments.
This price is correctly taken into the task cost.

Problem is that when I fill my progress this HW value is never added into the task real cost and so even when I define my task as 100% done I still have a remaining cost on this task with this value.
Have I done something wrong ?