Tasks are marked as late if their current progress is behind the status date. If you have been rescheduling tasks (as you should - there should be no incomplete work in the past) - the rescheduling "resets" the task status. Late tasks are not "as compared to baseline" - the Slipping Tasks filter or a custom RAG comparing [Finish] to [Baseline Finish] I think would suit your needs better.
|