View Single Post
 
Old 08-02-2015, 05:32 AM
BarryB BarryB is offline Windows 7 64bit Office 2013
Novice
 
Join Date: Apr 2015
Posts: 19
BarryB is on a distinguished road
Default

Hi

So I went back into my original file and re-set a baseline. I again updated the tasks to show the actual start and finish times my Site Manager gave me, while checking on future tasks which were 'Late'.

As I began to update the tasks as completed I noticed that tasks further down the schedule which were 'Late' began to show as 'On Schedule' or 'Future'. These shouldn't be because my project is running behind schedule and several of these now 'On Schedule' or 'Future' tasks should have been completed 3 days before the current Status Date.

Is this change happening because Project is automatically rescheduling tasks due to the project drifting from the original baseline schedule which I had set?

I would like to show tasks which are 'Late' against the baseline.

Thanks
Reply With Quote