07-19-2015, 09:53 AM
JulieS
Windows 7 64bit
Office 2013
Expert
Join Date: Dec 2011
Location: New England
Posts: 1,693
You should not assign resources to a summary task. The summary task's purpose is to summarize information from the subtasks. Take the resources off the summary tasks - save the baseline again.