Unhappy EVM on summary tasks

Hello,

I have some problem with the calculation of Earned value on summary tasks.
When I fill the %work done in a normal task : no problem EV is calculated, no problem.
But I have some resources that I have affected to a summary task.
In this case, I have the correct %work done calculated for my summary task based on sub tasks.
Bu EV for the summary task is calculated as SUM of EV from sub tasks and not as %work x Planned Value.
I thus get a Cost Variation between real cost and earned value.
Here is a screen shot of a small example :
(Sorry my MS Project version is in french so :
VA = EV
VC = CV
VP = PV
%travail = % work)