Quote:
Originally Posted by JulieS
Hi Sebastian,
If you know the formulas to calculate those values you can calculate them in spare (custom) fields. If you could share the formulas, I'll try to be more helpful walking you through the process.
|
Sir, first of all, thanks for answering to my post!!! The formulas are as follows:
Time Estimate at Completion (EACT): (BAC/SPI) / (BAC/months)
where BAC is Budget at Completion and SPI Schedule Performance Index.
[B]Estimate to Complete: EAC- AC
where EAC is Estimate at Completion and AC is Actual Cost of Work Performed)
[B]SPIxCPI: Just the multiplication of these two values.
I'd really appreciate if you could help me with this!!! Thanks sir!!!