I'm afraid it's not possible.

By definition, when linking you are setting an order based upon the predecessor's start or finish and the successor's start or finish. Link them how you *think* it will happen and then be prepared to adjust when the trials start.

I imagine some sort of decision about which trials starts when is made before the trials actually start?