For NEWCASE ---> LON/00AM/OLR/2014/0558 the end point would be
Critical Information Missing. Move on to Notify Parties Incomplete Application Received.
This would indicate the end point for cases to be the first TASKCOMP in column D for each case.
Is this assumption correct and applicable to every case ?