Want to total duration and date to 1st floor
New to the site and MS project
I am trying to tie my location on the first floor to a total duration. I want to be able to change a start date and have all of the locations change dates
All Plumbing Rough in on 1st floor - All HVAC Rough in on 1st Floor - I have 3 locations on the first floor – Lobby Registration – Entry Vestibule – Concierge Etc
Per total location area (see Example) can this be done in MS Project
Task Name Duration Start Finish Predecessors
Interior Finishes First Floor South - TOTAL 203 days Wed 12/31/14 Fri 10/16/15
Location Totals 3
Plumbing rough in 9 days Mon 6/8/15 Thu 6/18/15 47
Run gas piping 3 days Mon 6/8/15 Wed 6/10/15 47
HVAC rough in 9 days Mon 6/8/15 Thu 6/18/15 47
Task Name Duration Start Finish Predecessors
Lobby - Registration
Plumbing rough in 3 days Mon 6/8/15 Thu 6/10/15 47
Run gas piping 1 days Mon 6/8/15 Wed 6/8/15 47
HVAC rough in 9 days Mon 6/8/15 Thu 6/10/15 47
Task Name Duration Start Finish Predecessors
Entry Vestibule
Plumbing rough in 3 days Mon 6/11/15 Thu 6/14/15 47
Run gas piping 1 days Mon 6/9/15 Wed 6/9/15 47
HVAC rough in 9 days Mon 6/11/15 Thu 6/14/15 47
Task Name Duration Start Finish Predecessors
Concierges
Plumbing rough in 3 days Mon 6/15/15 Thu 6/18/15 47
Run gas piping 1 days Mon 6/10/15 Wed 6/10/15 47
HVAC rough in 9 days Mon 6/15/15 Thu 6/18/15 47
|