Bar chart
Hi,
I have the following situation:
Task - 3days - 04/05/2015 - 06/05/2015
When I change the duration from 3 to 2 days, obviously the length of the bar chart reduces accordingly.
When I change the "Hours per day" from 8 to 12 in the File > Options> Schedule, Project recalculate the duration from 3 to 2days but the length of the bar chart remains unchanged, still stretching over 3 days instead of 2.
Can anyone explain to me why it is like that?
Thank you.
|