Thread: Bar chart
View Single Post
 
Old 05-02-2015, 04:25 AM
fridos fridos is offline Windows 7 32bit Office 2007
Novice
 
Join Date: May 2011
Posts: 10
fridos is on a distinguished road
Default Bar chart

Hi,
I have the following situation:
Task - 3days - 04/05/2015 - 06/05/2015

When I change the duration from 3 to 2 days, obviously the length of the bar chart reduces accordingly.
When I change the "Hours per day" from 8 to 12 in the File > Options> Schedule, Project recalculate the duration from 3 to 2days but the length of the bar chart remains unchanged, still stretching over 3 days instead of 2.

Can anyone explain to me why it is like that?
Thank you.