Is Project giving you any sort of message? If you have resources assigned at above their max units - Project cannot fix the overallocation. If you have selected the option "Level only within available slack" it cannot delay tasks on the critical path.

I'm also not sure I follow when you say "Project has them all staring on the project start date with no modification .......they are set to auto scheduled."

This sounds more like tasks - not resources.