Default Link tasks

Hi,
I have a group of tasks 11, 12,13 to link with another group of tasks 21, 22,23 as shown in the attached able.

The type of relationship between task11 and 21, between task12 and task22, and between task13 and task23 is the same (FS+7)
This is easy to do. However let's imagine having a group of 100 tasks (task1 to task100) followed by another group of 100 tasks (task101 to task200). Typing the same type of relationship in the predecessor column is tiring and time consuming. Is there anyway to automate this and save time please?
Thanks for assisting me