Sorry, I must clarify the question.
The task is common to two resources: resource A with 100% unit, resource B with 0% unit, the task's duration is 5 days for example.
In the "Team Planner" view I can see the task for resource A, but I cannot see the same thing for resource B: how can I do this?
|