Team Planner view with 0% assignment
Hello,
I have a project file (v. 2010) with a resourcing pool, so my preferred view is the "Team Planner" one.
I have this problem: there are some tasks that have resources with a unit assignment of 0%, but in these cases, the "Team Planner" view doesn't show anything!
How can I visualize the task for a resource that has 0% units assignment in the "Team Planner" view?
Regards, codeghi
|