04-23-2015, 06:50 AM
JulieS
Windows 7 64bit
Office 2013
Expert
Join Date: Dec 2011
Location: New England
Posts: 1,693
I'm afraid I don't follow completely. Are you talking about tasks with a Finish Variance where Baseline Finish < Finish? Have you considered using the built-in Status Indicator field?
JulieS
View Public Profile