Default RAG Status on Project 2013

Can someone help?!

Created a plan in MS Project 2013 but need the RAG status to be based on the baselined dates.

e.g.
Task will go red if new date entered is after the baselined date.
But when baselined date is updated it will go to Green
Along with the % complete making the RAG blue when it hits 100%

Is there anyway this can be done?