Unless you are working with Fixed Duration tasks, you should be able to use the % complete test only without having to worry about the OR condition.

You may also find the built in filter "Late/Overbudget tasks assigned to..." filter is more to your need. Testing solely whether the task is incomplete will show all future tasks that you wouldn't expect to be complete.