Thread: [Solved] Major Project Guidance
View Single Post
 
Old 03-26-2015, 11:40 AM
JulieS JulieS is offline Windows 7 64bit Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

Quote:
First task:
Let’s assume I’m in the business of making phones – lots of different types. Duration is takes to make a phone is set – 4 weeks. Throwing more resources to it does not change, as there are set equipment limitations. Also, I would use a 24-hour calendar (not standard). However, I can make up to 4 phones in the 4 weeks, as the equipment use is not 100% the entire 4 weeks. Additionally, let's say I have 4 types of equipment with different max usage available (i.e. 80, 80, 60, 50)

I’d like to stagger productions of a new types of phone every couple weeks. As I schedule the phone productions, what is the best way to see when equipment is available for use (to stagger productions) or when something is overused in a given time.
You can certainly assign the 24 hours calendar either to the project (Project Information) or if you have a mixture of human and machine resources, set the 24 hours calendar as the base calendar for the machines and keep the human resources' calendar to the standard.

When you say the equipment is not used 100% for the tasks - you can certainly assign different assignment units to each task and resource pairing. You can also set different max units on the Resource Sheet View.

To see what else resources can do, look at the Resource Usage view and add the Remaining Availability field to the right hand side. If a resource is assigned at about its max units, the resource name will appear in red and the hours will appear red in the right hand side.

Quote:
Second task:
Next – I have pre-determined timeframes for phone production. So I want to plan it out in Project (I think this is baseline?) But of course, not everything goes to plan and sometimes the production is delayed a week. What is the best way of visual when and how often I miss deadlines?
Project will calculate variance for you by comparing baseline (start, finish, work, duration, cost) against actuals. You also can create deadlines in Project. They are not the same thing, however.

Quote:
Third task:
This involved forecasting. Assuming I’ve gotten tasks 1 and 2 covered, I should hopefully have an understanding of resource utilization and be able to maximize production by using my equipment more efficiently. With that said, if I wanted to increase my phone production for the following year, I want to be able to somehow project how much more equipment I’ll need.
You should be able to see overall resource utilization and help you tell when there are down periods in the cycle.
Reply With Quote