View Single Post
 
Old 02-23-2015, 01:03 AM
zcbeb10 zcbeb10 is offline Windows 7 64bit Office 2007
Novice
 
Join Date: Feb 2015
Posts: 2
zcbeb10 is on a distinguished road
Default Example formulas for default columns

Is there any way of getting hold of the existing formulas in the default cells in MS Project?

I want to create a customised formula for a new column:

--
Start1 = "Finish1" Date of "Predecessor" + 1 day or "Project start date" if "Predecessor" is 0/valueless
--

Essentially this is the same as the default formula for column "Start" with reference to "Finish1" instead of "Finish".

So if i had access to the default column formulas im sure i could work out new formulas for my new columns.

Alternatively if these are not available, does anyone have a good list of basic formulas for MS Project or can anyone help with my specific query above.


I am trying to create 2 scenarios with different timelines for the same tasks.

Many thanks for your time.
Reply With Quote