View Single Post
 
Old 02-11-2015, 02:42 PM
raminraiszadeh raminraiszadeh is offline Windows 7 64bit Office 2013
Novice
 
Join Date: Sep 2014
Posts: 22
raminraiszadeh is on a distinguished road
Default

Thanks very much Julie!

I spot-checked several tasks and their start/finish dates did not get affected by the project date changed (which is good).

At the time I changed the project start date, I had not created any baselines (which is also good).

A few of the tasks were 100% complete. These were also not impacted by the date change.

Question: Why did you ask about the baseline?

Thanks again!
Reply With Quote