What are the implications of changing project start date
View Single Post
02-09-2015, 04:07 PM
raminraiszadeh
Windows 7 64bit
Office 2013
Novice
Join Date: Sep 2014
Posts: 22
What are the implications of changing project start date
My project start date is set to 09/2014. What happens if I change the project start date to 02/2015?
I have tasks that started in 09/2014. What will happen to these and other tasks?
Thank you