Quote:
Originally Posted by JulieS View Post
If you have allowed tasks to be split during leveling, Project will take a task and "chunk" it into smaller pieces. As long as the task is not Fixed Duration, the splits (where the task is not working) will not count in the duration.
understood.
thank you.
how does one allow or not allow a task to be split?