View Single Post
 
Old 01-30-2015, 09:25 AM
leesc84 leesc84 is offline Windows 7 32bit Office 2010 32bit
Novice
 
Join Date: Jan 2015
Posts: 3
leesc84 is on a distinguished road
Default Planned Against Actual MSP 2010

Is there any where I can show how many working days was planned within a period, say a month from the baseline, and show how many was actually completed from the percentage complete a month later on a update.

For example on the 01/02 can I show I had planned 100 man days work in the month, and come the 01/03 when the next update is completed and when the percentages are updated we have only achieved 75 man days work.

If this is possible can I split these into critical activities and non.
Reply With Quote