Default resource assignment for multiple tasks

People,

Please support me as I cant solve the following:

There are two operation:
1. Check book duration 2 days
2. Read book duration 2 days
For 1st operation I would like to assign two Inst technicians
For 2nd operation I would like to assign two Inst technicians

12 hours is working hours for both operation but two technicians work 6 hours for operation 1, and 6 hours for operation 2 on the second day of work.

How to assign them properly, the system currently calculated the total hours as 96 hours but it must be 72

Your prompt feedback is highly desirable))))