Thread
:
MS Project - Start/end and duration.
View Single Post
01-15-2015, 06:31 PM
JulieS
Windows 7 64bit
Office 2013
Expert
Join Date: Dec 2011
Location: New England
Posts: 1,693
In addition to changing the hours per day, you also need to change the working time in the project calendar. Project tab, Change working time. Then change your default state and default end time to match what you have set in the calendar.
JulieS
View Public Profile
Find all posts by JulieS