my question is this: when you give SS + y days... you do not know how well the predecessor will proceed in those y days, which would enable the successor to start. how do you solve this problem?
also,
even if you just gave SS, you still dont know how well the predecessor will proceed after starting. for example, the sucessor may still depend on predecessor even after starting even though it just may have SS.
|