% completion changes finish date?
View Single Post
11-24-2014, 04:18 PM
JulieS
Windows 7 64bit
Office 2013
Expert
Join Date: Dec 2011
Location: New England
Posts: 1,693
When I open the file and press F9, I get immediate error messages about task 97.
I can reproduce your exact issue when mixing ALAP summary tasks with ASAP subtasks. The tasks split and the remainder of the task aligns with the ALAP constraints.