View Single Post
 
Old 11-24-2014, 08:25 AM
Mareike_# Mareike_# is offline Windows 7 64bit Office 2013
Novice
 
Join Date: Nov 2014
Posts: 3
Mareike_# is on a distinguished road
Default Costs are shifted when changing the timescale

Hello everybody,


with the conversion from MS Project 2010 to 2013 the following thing happens if I edit the timescale in the view "Task: usage":


If the Bottom Tier is on the unit weeks or days, the costs are allocated correctly.

When I switch the Bottom tier to the unit month, my costs and working hours move to the previous month.

That was not the case in MS Project 2010. Do you know how to get the costs and working time back to the right month?


Can someone please explain the background of this phenomenon and how I can remove it again.


Many Thanks and Regards

Mareike
Reply With Quote