Thread: [Solved] Budget cost on early stages
View Single Post
 
Old 10-29-2014, 01:58 PM
ketanco ketanco is offline Windows 7 64bit Office 2010 64bit
Expert
 
Join Date: Dec 2011
Posts: 279
ketanco is on a distinguished road
Default

to see a cost distribution by time you can first assign fixed costs to the item summary tasks as you wrote in your original post.

then go to task view. select cummulative cost. you will see a cumulative cost distribution by time and then you can copy paste these to excel and draw a nice graph
Reply With Quote