Thread: [Solved] Weekend Working
View Single Post
 
Old 10-27-2014, 11:59 AM
Planner18 Planner18 is offline Windows 8 Office 2010 32bit
Novice
 
Join Date: Oct 2014
Posts: 14
Planner18 will become famous soon enough
Default Weekend Working

I am looking for some advice on how to manage weekend working in Project 2010.

We have several projects connected to a centralise resource pool containing over 80 resources. Most of the resources are shared across the various projects. One project is late and wishes to show a few resources working over a number of weekends on a several tasks in an attempt to catch up. These resources are used on other projects as well.

My question what is the best way of doing this, bearing in mind, the resource pool is used to produce a total resource profile / forecast for the programme?

Any advice would be appreciated.

Thanks

Planner18