Work between Two Dates
View Single Post
10-06-2014, 06:10 PM
JulieS
Windows 7 64bit
Office 2013
Expert
Join Date: Dec 2011
Location: New England
Posts: 1,693
Set the task as fixed duration, non-effort driven, autoscheduled. You can then assign the resources (Task Form) and enter the amount of work. Project will calculate the units required to spread the work out over the duration.
I hope this helps.
JulieS