Thread
:
keeping certain items separate from overall % calculation
View Single Post
09-17-2014, 05:43 AM
ketanco
Windows 7 64bit
Office 2010 64bit
Expert
Join Date: Dec 2011
Posts: 279
so in the other schedulers schedule, when although he assigned zero work to submittals, but gave them durations, then his submittals are still taken into account for % complete correct?
ketanco
View Public Profile
Find all posts by ketanco