Thread: [Solved] 2 Shift - Project Calendar
View Single Post
 
Old 09-08-2014, 10:42 AM
JulieS JulieS is offline Windows 7 64bit Office 2013
Expert
 
Join Date: Dec 2011
Location: New England
Posts: 1,693
JulieS will become famous soon enough
Default

See if the attached file helps. I have a project calendar with working times from 7:00 am to 12:00 am with breaks during when the resources should be not working. My definition of "day" in File > Options, Schedule is 16 hours, week is 80 hours, default start and finish align with Project calendar.

I have a first shift calendar from 07:00 to 3:30 with a half-hour lunch. I have a second shift calendar from 3:30 pm to 12:00 am with a half-hour lunch. I have two resources each one assigned to one of the calendars.