See if the attached file helps. I have a project calendar with working times from 7:00 am to 12:00 am with breaks during when the resources should be not working. My definition of "day" in File > Options, Schedule is 16 hours, week is 80 hours, default start and finish align with Project calendar.
I have a first shift calendar from 07:00 to 3:30 with a half-hour lunch. I have a second shift calendar from 3:30 pm to 12:00 am with a half-hour lunch. I have two resources each one assigned to one of the calendars.
|